Inputs

Cables

The Cables card on the Electrical tab — whether cable runs are routed and measured, and the three allowances added to the DC string-cable total.

The Cables card decides whether the application routes and measures the cables between the tables, the inverters or string monitoring boxes and the control rooms, and, when it does, what allowances are added to the DC string-cable total. It is the third card on the Electrical tab, after the inverter card and the ACCB & Transformer card (Transformer in a central-inverter design — see ACCB and transformers). Routing is off as shipped, because it is the slow step on a large plant. The equipment is placed and counted whether or not the cables are traced.

How the runs are routed once the option is on — the patterns, the trenches and the medium-voltage network — is on Cable routing. This page covers the card.

The Cables card at its defaults: Calculate cables unticked, inter-module lead 0.00 m/module, the string return run unticked, and DC cable slack 10.0 %.
The Cables card

The fields

FieldDefaultRangeWhat it does
Calculate cablesoff—Routes every DC and AC run on the next Generate Layout and reports the lengths
Inter-module lead0.00 m/module0.00–2.00 m/moduleExtra string cable per module for the leads between modules, counted once per string. Fixed-tilt tables only
String return run along tableoff—Tick for daisy-chain wiring: adds one conductor's run back along the table per string. Fixed-tilt tables only
DC cable slack10.0 %0.0–30.0 %Slack and wastage added to the DC string-cable total, trackers included

The tick and all three allowances are saved in the project file and come back when it is reopened. They are also inputs to the run: change any of them after generating and the layout is marked out of date until you generate again. See Out-of-date results.

Calculate cables

Off by default. With it off, the layout is generated, the inverters or monitoring boxes are placed and counted, and no cable is routed. With it on, the application traces every run on the next Generate Layout and reports its length.

What gets traced depends on the design, because the conversion happens in a different place:

RunFromTo
String DC cableEach table (MMS)Its string inverter
AC cableEach string inverterIts ICR

The inverter converts in the field, so the run into the control room is AC. The totals appear on the String DC cable (m) and AC cable to ICR (m) rows of the Summary view.

Medium-voltage runs from the control rooms to the main control room are routed in both designs, once a main control room has been placed and the layout generated again with this option on.

The performance notice

Ticking the box raises Cable Calculation — Performance Notice before anything is enabled. It reads: Cable calculation can take a long time on large or complex layouts. — It is recommended to generate the plant layout first without cable calculation, review the result, and then enable cable calculation for the final run. Do you want to enable cable calculation now?

The Cable Calculation — Performance Notice with its text and the Enable Now and Not Now (Recommended) buttons.
The performance notice
ButtonWhat it does
Enable NowLeaves the box ticked. Cables are routed on the next Generate Layout
Not Now (Recommended)The default. Unticks the box again

Opening a saved project that had the option on does not raise the notice.

The Cables card with Calculate cables ticked.
Cable calculation switched on

Take the recommendation on a plant you have not laid out before. Cable routing is the slow step on a large plant, and it is the step whose result you are least likely to keep: change the table configuration, the perimeter road, the ICR block or the strings per inverter, and every run is traced again from scratch.

What you still get with cables off

  • The inverter and monitoring box counts are computed anyway. So are their ratings, the central inverter count, and everything downstream that depends on them — the AC capacity, the DC / AC ratio, the single-line diagram and the bill of materials.
  • The cable rows of the Summary view show a dash. A — on any row of the CABLES group means the value was not computed, not that it is zero.
  • The three cable rows of the Layers popover stay disabled, and the cable layers are left out of the CAD export.
  • The cable schedule can still be exported. Its lengths are then straight lines between the ends, increased by 15 %, rather than routed lengths. See The cable schedule.

Everything else about the design is final. Only the cable numbers are missing, and one more run with the box ticked fills them in.

The three DC allowances

The routed length of a string cable is the distance from the table to the inverter or monitoring box. Three further figures turn that into a quantity you can order against, and they are added to the DC string-cable total only.

Inter-module lead

Inter-module lead is extra string cable allowed per module for the leads that join one module to the next, counted once per string. It ships at 0.00 m per module, because the module supplier normally provides these leads with the modules. Enter a figure only when your procurement buys that cable separately. It applies to fixed-tilt tables only.

String return run along table

How much string cable a table needs depends on how its strings are wired.

WiringThe string's two leadsSetting
LeapfrogExit at the same end of the tableLeave String return run along table unticked — the default
Daisy-chainEnd at opposite ends of the table, so one conductor must run back along the table to exit beside the otherTick String return run along table, and that run back along the table is added per string

It applies to fixed-tilt tables only.

DC cable slack

DC cable slack is the slack and wastage added to the DC string-cable total, as a percentage. It ships at 10 %, the bill-of-quantity convention. Unlike the other two allowances it applies to every design, tracker plants included.

Where to go next

On this page