Reference

Glossary

Every BESS term the application's own glossary defines, grouped by dispatch and sizing, battery lifecycle, tariffs and pricing, financial terms, and units.

Grouped the way the application's own glossary groups them: dispatch and sizing, battery lifecycle, tariffs and time-of-day, financial terms, and units. Where a term ships with a default value or range, it is given here.

Dispatch and sizing

DFR (Delivery Fulfilment Ratio) — The fraction of required or contracted energy actually delivered in a given window: delivered ÷ required. Tracked at four granularities — 15-minute, Peak-hour, Off-Peak and Overall Monthly — plus an Annual figure. Falling short of a window's target triggers a shortfall penalty. Default targets: 15-min DFR Target 0% (off), Peak-hour DFR Target 90%, Off-Peak DFR Target 80%, Overall Monthly DFR 90%, Annual DFR Target 0% (off). See Delivery Fulfilment Ratio (DFR).

Contracted Capacity (CC) — The firm load or capacity the plant is obligated to serve, either a fixed MW value or a time-varying 15-minute profile. DFR and the CUF cap are both measured against it. Default Fixed Value is 1.6 MW.

Dispatch — The per-15-minute rule deciding whether the battery charges, discharges or idles at each simulation step. The application selects one of five mutually exclusive dispatch branches per run: Standalone, CC-firming, Generation-charged Peak-Shift, Peak/Off-Peak, and Cycle-mode. See How dispatch works.

  • Peak-shift — The Peak-Shift dispatch checkbox's mode: generation charges the battery first, and it discharges only inside the selected Peak window to meet the Contracted Capacity, with no obligation — and no penalty — outside that window. Off by default.
  • CC-firming — The dispatch used when the Peak-hour set is left explicitly empty, all 24 hour checkboxes unticked: it firms the Contracted Capacity every hour of the day instead of only in a Peak window.

RTE (Round-Trip Efficiency) — The fraction of energy recovered from one full charge/discharge cycle, including auxiliary losses. The model applies the square root of RTE separately to the charge leg and the discharge leg. Default 78%, range 50–99%.

DoD (Depth of Discharge) — The fraction of nameplate energy usable per cycle. Default 90%, range 50–100%.

SOH (State of Health) — The battery's remaining capacity relative to nameplate as it ages; usable energy is nameplate × DoD × SOH. Starting SOH default 100%, range 50–100%. See The battery model.

C-rate — The BESS power-to-energy sizing ratio, Power ÷ Energy (MW ÷ MWh). Default 0.25, range 0.1–2.0.

Battery lifecycle

Battery EOL (End-of-Life) — The point at which the pack is considered exhausted and is replaced or augmented. Selectable basis, default In Years: in years (default 20, range 5–30) or in total cycles (Rated Cycle Life default 6000, range 100–20,000). See Degradation and end-of-life.

EFC (Equivalent Full Cycle) — One full nameplate-energy charge/discharge equivalent. Annual EFC throughput is annual discharge energy ÷ rated usable energy, and it accumulates against the Rated Cycle Life to find the cycle-basis end-of-life year.

Replacement vs Augmentation — The two end-of-life strategies. Replacement is a full pack swap at the end-of-life year — the default. Augmentation tops the pack up with additional MWh tranches instead, either automatically restoring nameplate every end-of-life-interval year — the default sub-mode — or on a manually scheduled table of year and capacity. A new tranche degrades from its own install year and books its own CAPEX.

Tariffs, pricing and time-of-day

PPA tariff — The contracted price paid per kWh of delivered energy. Default 5.0 Rs/kWh, range ≥ 0.1 Rs/kWh; may escalate annually via PPA Tariff Escalation, default 0%/yr. See Tariffs, export and penalties.

Export price — The price paid for surplus energy sold to a third party — a flat rate or a 15-minute CSV series, such as a power-exchange clearing-price feed — distinct from the PPA tariff. Default Fixed Price mode, 0.0 Rs/kWh.

Grid-charging price — The price paid for grid energy used to charge the battery: always, on a Standalone project; only as worst-case backup, on a generation-backed one. Default 0.0 Rs/kWh.

CUF cap (Annual CUF Cap) — An optional ceiling on how much delivered energy is paid at the PPA tariff: cap (MWh) = cap % × Contracted Capacity × 8760. Energy above the cap is paid at the export price instead. Off by default; cap % default 28.0 when enabled.

ToD (Time-of-Day) peak / off-peak — The 24 hourly checkboxes on the ⏰ Peak tab, splitting the day into Peak hours (the battery discharges first, then charges from any excess) and Off-Peak hours (the battery charges first, and the remainder meets the Contracted Capacity). Default ticked: 18:00 to 21:00, 4 hours.

Financial terms

IRR (Internal Rate of Return) — The discount rate at which project NPV equals zero. The headline Project IRR excludes debt, tax and salvage value. See Return metrics.

Equity IRR — IRR of the levered equity cash-flow stream: EBITDA minus interest, principal and levered tax. Computed only when Enable debt (levered analysis) is on. See Debt and tax.

NPV (Net Present Value) — The discounted sum of project cash flows at the Discount Rate (NPV), default 10%.

Payback (simple / discounted) — The year cumulative — or discounted-cumulative — project cash flow first turns non-negative, linearly interpolated within the year.

DSCR (Debt-Service Coverage Ratio) — (EBITDA minus levered tax minus reinvestment) ÷ (interest plus principal) for the year, reported as a minimum and an average across the debt tenor. Only meaningful when Enable debt (levered analysis) is on.

DSRA (Debt-Service Reserve Account) — A reserve funded upfront alongside equity, sized as (DSRA months ÷ 12) × the first year's interest plus principal. Default 0 months.

MoIC (Multiple on Invested Capital) — Sum of positive cash inflows ÷ initial outlay.

PI (Profitability Index) — (NPV + CAPEX) ÷ CAPEX. A PI above 1 is value-accretive.

WACC (Weighted Average Cost of Capital) — The after-tax blended cost of equity and debt, computed only for levered projects.

LCOE (Levelised Cost of Energy) — Total lifecycle cost ÷ discounted energy, in Rs/kWh. The energy basis is selectable on the 🏦 Finance tab, default Energy delivered to load (default).

LCOS (Levelised Cost of Storage) — The same shape as LCOE, but over BESS-only CAPEX, OPEX and reinvestment, divided by discounted battery-discharge throughput — the cost of every kWh that actually passes through the battery.

Terminal / Salvage value — A residual value credited at the end of Project Life, as a % of total CAPEX. Default 0.0%, range 0–100%.

Working-capital carrying cost — A recurring finance cost modelling the gap between PPA billing and offtaker payment: receivables = annual revenue × (lag days ÷ 365); cost = receivables × (Working-Capital Rate + WC Facility Fee − Late-Payment Surcharge), deductible against EBITDA and tax. Zero when Receivable Lag is 0, the default. See Working capital.

Units

Crore (Cr) — Rs 1,00,00,000. The unit CAPEX, NPV and the Financials tab's figures are quoted in.

Lakh (Lac) — Rs 1,00,000. The unit O&M costs and DFR-shortfall penalties are quoted in.

MWh ↔ kWh — ×1000. The DFR-shortfall penalty formula, for example, converts an MWh shortfall to kWh by multiplying by 1000 before pricing it at the tariff.

15-min base — The simulation's native time step: 0.25 hours per step, 35,040 steps for a full year.

Where to go next

On this page